【多选题】
Which two statements are true regarding VMware vSphere Flash Read Cache (vFRC)? (Choose two.)___
A. Cache fills and cache evictions happen in the granularity of a cache block size.
B. vFRC caches data from both read and write I/Os, but write I/Os are always serviced by the underlying storage.
C. vFRC caches data from both read and write I/Os, but write I/Os are always serviced by the underlying cache data.
D. Cache fills and cache evictions happen in the granularity of the disk block size.
查看试卷,进入试卷练习
微信扫一扫,开始刷题

答案
AB
解析
暂无解析
相关试题
【多选题】
What are two possible causes of Storage Distributed Resource Scheduler (SDRS) being disabled on one or more virtual machine disks in a datastore cluster? (Choose two.)___
A. The virtual machine has vSphere Fault Tolerance disabled.
B. The virtual machine is a template.
C. The virtual machine swap file is on a shared datastore.
D. The disk is a CD-ROM/ISO file.
【多选题】
An administrator attempts to install vCenter Single Sign-On Server. The installer returns an error message indicating that the installation failed. Prior to the installation, all setup prerequisites were met. The administrator has generated a vCenter Server Single Sign-On support bundle. Which two files should the administrator analyze to determine the cause of the failure? (Choose two.)___
A. Server\utils\logs\imsTrace.log
B. Server\utils\logs\install.txt
C. %TEMP%\utils\logs\vminst.log
D. %TEMP%\vminst.log
【多选题】
An administrator is unable to remove an ESXi 6.x host from a vSphere Distributed Switch. What are two likely reasons for this issue? (Choose two.)___
A. Vmkernel interfaces on the switch are still in use.
B. VM Network port group adapters are connected to different switch.
C. Physical NICs are migrated to different switch.
D. VM Network adapters are connected to this switch.
【多选题】
Which two Identity Sources are available to add for vCenter Single Sign-On authentication? (Choose two.)___
A. LocalOS
B. OpenLDAP
C. NIS as an LDAP Server
D. VCMSDS
【多选题】
What are three goals of resource management within a cluster? (Choose three.)___
A. To prevent virtual machines from monopolizing resources and to guarantee predictable service rates.
B. To exploit undercommitted resources and overcommit with graceful degradation.
C. To provide solutions to potential problems that you might encounter when using vCenter Server.
D. To control the relative importance of virtual machines and provide flexible dynamic partitioning.
E. To provide additional network administration capabilities.
【多选题】
Which three actions can be taken as a result of executing the vSphere Update Manager 6.x scan and remediation wizards? (Choose three.)___
A. Install and upgrade software in virtual machines.
B. Upgrade the firmware on ESXi host devices.
C. Upgrade and Patch ESXi hosts.
D. Install and update third-party software on hosts.
E. Upgrade virtual machine hardware.
【多选题】
Which two statements are true about deploying and using vSphere Replication? (Choose two.)___
A. ESXi hosts managed by a single vCenter Server instance require a connection between the two vSphere Replication appliances.
B. Sites managed by different vCenter Server instances require a connection between the two vSphere Replication appliances.
C. Sites managed by different vCenter Server instances require the use of Site Recovery Manager and a connection between the two vSphere Replication appliances.
D. ESXi hosts managed by a single vCenter Server instance require a single vSphere Replication appliance.
【多选题】
An administrator is attempting to power on a virtual machine, but the task is hanging at 95%. What three scenarios best explain why this problem is happening? (Choose three.)___
A. A virtual machine question is currently being posed to the administrator.
B. Another task for the virtual machine or other component is already in progress.
C. The VMware High Availability cluster has insufficient resources to guarantee failover.
D. The host has lost access to the storage device containing the virtual machine files.
E. The host is under resource contention and unable to power on the virtual machine.
【多选题】
Which three features are not supported when using Fault Tolerance in vSphere 6.x? (Choose three.)___
A. Virtual Volumes (VVOLS)
B. Storage vMotion
C. Virtual Machine Component Protection
D. vMotion
E. vSphere Distributed Switches
【多选题】
Which two storage controller configurations can be used with Virtual SAN? (Choose two.)___
A. SAS controllers in Passthrough mode
B. SAS controllers in RAID0 mode
C. SAS controllers in RAID1 mode
D. SAS controllers in RAID10 mode
【多选题】
Which three are requirements when using vMotion to move a virtual machine across vCenter Server systems? (Choose three.)___
A. Both vCenter Servers must be using Enhanced Linked Mode.
B. Both vCenter Servers must be in the same Single Sign-On Domain.
C. Time must be synchronized.
D. Duplicate VM MAC addresses must be configured.
E. Both vCenter Servers must have High Availability enabled on source and destination clusters.
【多选题】
Which two components can be used when configuring Enhanced Linked Mode? (Choose two.)___
A. vCenter Server Appliance
B. vRealize Operations Manager
C. vSphere Management Appliance
D. vCenter Server for Windows
【多选题】
An organization has a number of virtual machines that would benefit from Fault Tolerance. These include: <A single vCPU Apache Server> < A dual vCPU vCenter Server> < A quad vCPU SQL Server> <An eight vCPU Hadoop Server>. Which two virtual machines can be configured to use VMware Fault Tolerance? (Choose two.)___
A. Apache Server
B. vCenter Server
C. SQL Server
D. Hadoop Server
【多选题】
Which two badges are major badges in vRealize Operations? (Choose two.)___
A. Risk
B. Efficency
C. Workload
D. Faults
【多选题】
An administrator is deploying multiple Windows 2003 Virtual Machines from the same template. What two steps should be taken to avoid network conflicts? (Choose two.)___
A. Customize the guest operating system.
B. Install VMware Tools into the new virtual machines.
C. Copy the Microsoft Sysprep tools onto the vCenter Server system.
D. Ensure the e1000 vmnic is selected for each new virtual machine.
【多选题】
Which three conditions would prevent Storage I/O Control from being enabled on a group of datastores? (Choose three.)___
A. The datastores planned for the solution are used by different vSphere clusters.
B. A datastore planned for the solution is configured as a Raw Device Mapping file.
C. A datastore planned for the solution has three extents.
D. A datastore planned for the solution is configured as NFS.
E. The organization has an Enterprise license.
【多选题】
Which two actions are prerequisites to adding ESXi 6.x hosts to a vSphere Distributed Switch? (Choose two.)___
A. Verify that there is at least one Distributed Port Group on the Distributed Switch.
B. Verify that the Distributed Port Group have active uplinks configured in its teaming and failover policy.
C. Verify that the
D. istributed Switch has been configured with a Network Profile.
【多选题】
An organization has configured Distributed Power Management (DPM) on a vSphere 6 cluster. The organization wants to be alerted when an ESXi host has been powered down by DPM. Which two options represent the type and name of the alarm that would accomplish this? (Choose two.)___
A. DrsEnteringStandbyModeEvent
B. DrsEnteredStandbyModeEvent
C. Event-based
D. Condition-based
【多选题】
Which two allow for the disabling of Network Rollback operations? (Choose two.)___
A. Modifying the vpxd advanded configuration options and adding the config.vpxd.network.rollback key
B. Modifying the C:\ProgramData\VMware\CIS\cfg\vmware-vpx\vpxd.cfg file and adjusting the<rollback> xml tag
C. Modifying the C:\ProgramData\VMware\CIS\cfg\vmware-vpx\vpxd.cfg file and adjusting the <networkrollback> xml tag
D. Modifying the C:\ProgramData\VMware\CIS\cfg\vmware-vpx\firstboot\vpxd-service- spec.prop file and adjusting the <rollback> xml tag
【多选题】
An administrator is tasked with performing a vMotion migration of a virtual machine. The virtual machine is configured as follows: <vSphere Flash Read Cache (vFRC) enabled> <Is part of a Distributed Resource Cluster (DRS) Cluster> Which two statements are true? (Choose two.)___
A. Each ESXi host in the cluster supports multiple virtual flash resources.
B. Each ESXi host in the cluster supports one virtual flash resource.
C. DRS treats powered-on virtual machines with Flash Read Cache as having a preferred affinity to their current host and moves them only for mandatory reasons.
D. DRS treats powered-on virtual machines with Flash Read Cache as having a required affinity to their current host and does not move them.
【多选题】
An administrator is using the Host Failures to Tolerate Admission Control Policy for a vSphere High Availability ___ cluster. When configuring this setting on the cluster, the administrator sees this error message: <Insufficient resources to satisfy HA failover level on cluster > What are two likely causes for the error? (Choose two.)(AB)
A. The hosts in the cluster are disconnected.
B. A host in the cluster is displaying an HA error.
C.
D. istributed Resource Scheduler has not been configured on the cluster.
【多选题】
What are two ways to identify TCP/IP stack information? (Choose two.)___
A. Using the vSphere Web Client
B. Using esxcli network ip netstack
C. Using esxcfg-netstack
D. Using the vSphere Client
【多选题】
Which two actions are required when enabling vFlash Read Cache for a virtual machine's virtual disk? (Choose two.)___
A. A value in the Virtual Flash Read Cache text box must be entered.
B. A Flash Resource Pool for Cache size reservation must be entered.
C. The Device backing and the block size must be configured.
D. The
E. nable virtual flash host swap cache check box must be selected.
【多选题】
What two IT infrastructure components are virtualized by vSphere Essentials? (Choose two.)___
A. Networks
B. Applications
C. Storage
D. Management
【多选题】
When attempting to access a virtual machine, an administrator is unable to login using the vSphere credentials. What two options are probable causes of the authentication failure? (Choose two.)___
A. The vSphere credentials have not been granted permissions.
B. The vSphere credentials are granted read-only permissions.
C. The vSphere credentials are granted no-access permissions.
D. The vSphere credentials are not a member of the local administrator group.
【多选题】
An administrator is performing a scripted installation of ESXi 6.x. In which three locations does the script need to be? (Choose three.)___
A. PXE Server
B. HTTPS
C. FTP
D. NFS
E. VVOLs Datastore
【多选题】
In order for a company to meet regulatory requirements, all ESXi 6.x Hosts must be configured to direct logs to a syslog server. What are two ways ESXi hosts can configured for this action? (Choose two)___
A. Use the esxcli system syslog command.
B. Edit them in the ESXi host Advanced System Settings.
C. From the Syslog collector user interface of the Web Client.
D. Syslog logging is not available for
E. SXi Hosts.
【多选题】
Which three actions can be executed when an alarm is triggered? (Choose three.)___
A. Send an email.
B. Send an SNMP trap.
C. Run a script or command.
D. Run an Orchestrator workflow.
E. Send a trigger to syslog.
【多选题】
An administrator is attempting to power on a virtual machine, but is unable to do so. Which two reasons are probable causes of the failure? (Choose two.)___
A. Storage access to the virtual machine swap file has been lost.
B. One of the virtual machine VMDK files is locked.
C. Virtual machine is running CentOS 7.0 64-bit.
D. Virtual machine has Hyper-Threading enabled.
【多选题】
An administrator has configured a host profile so that ESXi 6.x hosts will point to the corporate NTP server for time synchronization. The NTP server is located at 10.0.30.213, but time has not been synchronized properly across the ESXi hosts. The administrator reviews Host Profile settings as shown in the Exhibit. Which two steps are required to resolve the issue? (Choose two.)___
A. Correct the NTP server IP address.
B. Check the host for host profile compliance.
C. Remediate the host based on the updated host profile.
D. Change the NTP server to the FQDN as IP Addresses are not supported.
【多选题】
An administrator is attempting to migrate a large Hadoop virtual machine using vMotion. The administrator notices a delay when the machine is quiesced. The Hadoop virtual machine is processing many transactions a second to an in-memory database. Which two actions would help reduce the amount of time needed to perform a vMotion on this virtual machine? (Choose two.)___
A. Use multiple NICs for the vMotion vmkernel port.
B. Use a 10Gbps Network card for the vMotion vmkernel port.
C. Add an additional management network to help transmit the data quicker.
D. Disable Fault Tolerance before performing the vMotion.
【多选题】
An administrator is installing a new network card in an ESXi 6.x host that is part of a vSphere cluster. When the host is placed into maintenance mode, the vSphere Web Client displays the progress bar at 2% for over 30 minutes. Which two are likely reasons for this occurrence? (Choose two.)___
A. Maintenance mode is unable to migrate all virtual machines from the host.
B. There is a large number of virtual machines that must be migrated from the host.
C. VMware High Availability is in the process of reconfiguring the cluster.
D. Each virtual machine on the
E. SXi host must be reconfigured to recognize the new adapter.
【多选题】
Which two events happen when Distributed Resource Scheduler (DRS) is disabled? (Choose two.)___
A. The cluster's resource pool heirarchy and affinity rules are re-established when DRS is turned back on.
B. The cluster's resource pool hierarchy and affinity rules are not re-established when DRS is turned back on.
C. The cluster's resource pools are removed from the cluster.
D. The cluster's resource pools are removed from the cluster and assigned to the hosts.
【多选题】
Which two networking connection types can be configured on a virtual switch? (Choose two.)___
A. Virtual machine portgroups
B. VMkernel services (such as NFS, iSCSI, or vMotion) to the physical network
C. Web services over the Management Network
D. NFS and FCoE storage services
【多选题】
An administrator creates a DRS cluster of eight ESXi 6.x hosts. There are 10 virtual machines balanced across the hosts. An attempt to place the first host into maintenance mode fails. What are two reasons that the host failed to enter maintenance mode? (Choose two.)___
A. The DRS cluster Automation Level is set to Partially Automated mode.
B. One of the virtual machines on the ESXi Host entering maintenance mode is configured with a DRS Host affinity rule Should run on hosts in group.
C. One of the virtual machines on the ESXi Host entering maintenance mode is configured with a DRS Host affinity rule Must run on hosts in group.
D. One of the virtual machines on the
E. SXi Host entering maintenance mode is configured with an individual Automation Level set to Partially Automated.
【多选题】
When modifying a vApp, which two vSphere entities can be added? (Choose two.)___
A. A resource pool
B. A network pool
C. A vApp
D. A folder
【多选题】
From which two locations in the inventory hierarchy can you deploy a virtual machine using a template? (Choose two.)___
A. Directly from the template.
B. From a compute resource.
C. From an existing virtual machine.
D. From a Datastore.
【多选题】
A company has decided to implement Virtual SAN within their vSphere 6.x environment. The Virtual SAN cluster will be composed of three ESXi 6.x hosts that are on the Virtual SAN Ready Node list. Each ESXi host includes: <Two SAS Controllers that support Passthrough Mode> < Four Solid State Drives (SSDs) 1TB in size each> <20 SAS Magnetic Disks (MDs) 1TB in size each> <The SSDs and MDs are evenly split between the two SAS controllers>. The company will pilot a Virtual SAN cluster utilizing VMware best practices while maximizing storage capacity. The Virtual SAN cluster will use Manual Mode. Which two Disk Group configurations would meet the stated configuration requirements? (Choose two.)___
A. 4 disk groups with 1 SSD and 5 MDs each
B. 2 disk groups with 1 SSD and 7 MDs each
C. 2 disk groups with 2 SSDs and 7 MDs each
D. 2 disk groups with 1 SSD and 10 MDs each
【多选题】
A physical Windows 2008 R2 Server is converted to a virtual machine using VMware vCenter Converter. Upon completion of the conversion and subsequent power on operation, the virtual machine fails to boot and the message below is observed in the Console of the virtual machine: <STOP 0x0000007B INACCESSIBLE_BOOT_DEVICE>. Which two potential issues may be causing this boot failure? (Choose two.)___
A. An incorrect SCSI controller was selected during conversion.
B. Incompatible software drivers were migrated into the virtual machine from the source machine.
C. The vmdk file backing the virtual machine was thick provisioned.
D. A snapshot was taken immediately after the conversion completed.
【多选题】
An administrator is configuring the Failover Order option on a vSphere Distributed Switch. Which two options should be used with IP-hash load balancing? (Choose two.)___
A. Active Uplinks
B. Standby Uplinks
C. Unused Uplinks
D. Override Failover Order
推荐试题
【单选题】
一名指导委员会成员提交了一项新请求,这项请求似乎没有等到充分考虑,可能会对项目产生负面影响,项目经理下一步应该怎么做?
A. 评估该请求的影响
B. 记录该请求,并将其提交给变更控制委员会.
C. 要求支持的成员说服该指导委员会成员撤回请求.
D. 拒绝该请求,并告知该指导委员会成员拒绝的原因.
【单选题】
一团队成员电话告知项目经理,称某一系统的实际速度与预计速度存在偏差。项目经理很吃惊,因为在计划阶段做绩效衡量时没发现此问题。如果项目经理开始评估是否要对偏差作出应对计划时,项目经理处于项目的哪个管理过程?
A. 启动
B. 执行
C. 监控
D. 收尾
【单选题】
渐进明细是结合了项目的一次性和独特性的特点。编制项目计划的过程中,渐进明细在以下哪个方面也是重要的:
A. 假设
B. 限制条件
C. 项目管理信息系统
D. 组织政策和程序
【单选题】
项目团队成员因杰出工作和满足项目成本目标而获得奖励,高级经理向项目经理确认谁可以获得奖励,项目经理可以在哪里获得此奖励的定义标准和频率?
A. 责任分配矩阵(RAM)
B. 项目管理计划
C. 人员解散计划
D. 资源管理计划
【单选题】
审查项目管理计划时,项目经理确定成本指数为 0.8,而进度绩效指数为 0.7,发生下列一项?
A. 关键相关方未充分参与
B. 项目执行超前
C. 项目执行欠佳
D. 项目范围蔓延
【单选题】
在一个产品开发项目结束时,客户满意度调查结果显示客户对于多个有价值的功能未包含在交付成果中感到失望。这些调查结果的可能原因是什么?
A. 工作分解结构定义不良
B. 需求定义不良
C. 风险登记册未保持更新
D. 团队在地理上是分散的
【单选题】
一名严苛的项目相关方坚持要增加项目需求,项目经理希望满足该请求,但是该请求与商业需求不一致。项目经理应该怎么做?
A. 仅批准预算内且与商业需求一致的需求
B. 将该需求提交给变更控制委员会
C. 同发起人一起审查该需求是否与项目范围不一致
D. 拒绝该请求并通知相关方
【单选题】
一项调查显示执行一个项目的最低可能成本为 1 亿美元。进一步调查同类项目比估算多 25%,而另一个项目成本比最低成本估算多三倍。使用提供的估算,下列哪一项应作为成本估算?
A. $1 亿美元
B. $1.5 亿美元
C. $2 亿美元
D. $2.5 亿美元
【单选题】
您的项目团队遇到一个任何成员以前都未遭遇过的问题。您需要为可能的解决方案出谋划策。您愿意使用下列哪种工具?
A. 思维导图
B. 挣值分析
C. 主生产进度规划
D. 时序划分
【单选题】
加入一个施工项目后,项目经理得知需要超过 90 天的时间才能收到一个施工许可,结果,预期开始时间可能被延迟,提交项目章程供批准之前,项目经理应该审查什么?
A. 事业环境因素
B. 组织过程资产
C. 风险登记册
D. 风险管理计划
【单选题】
客户对一个项目采取竞争性投标。客户规定项目成本为 150 万美元。年收入 50 万美元的 X 投标方,也参与该招标过程。该潜在客户项目获得的年净现金流为 25 万美元。根据 X 投标方的情况,在这种情况下投资回收期是多长时间?
A. 半年
B. 2 年
C. 3 年
D. 6 年
【单选题】
为什么项目验收标准是项目范围文件的重要组成部分?
A. 能让项目相关方接受产品
B. 它表示对需求的签署验收
C. 它确定产品的满足条件
D. 它定义了确认项目相关方需求的正式方式
【单选题】
在某个项目预计工期进行到一年时,项目经理发现实际成本为 75,000 美元,而项目预算为 100,000 美元,经过详细分析之后,项目经理发现项目活动已完成 60%,委员会决定未来开支将保持在目前水平。那么项目的完工估算是多少?
A. 25,000 美元
B. 50,000 美元
C. 60,000 美元
D. 91,667 美元
【单选题】
ABC 公司通常用年和法来计算资产的折旧。他们花 1.7 万元买了一台计算机,估计三年后能卖 2000 元。那么第三年的折旧是多少?
A. 5000元
B. 4500元
C. 7500元
D. 2500 元
【单选题】
项目经理已经完成了收集相关方需求的工作。并且必须在即将召开的指导委员会上发布项目进度计划,在制定项目进度计划之前,项目经理应该做什么?
A. 创建工作分解结构
B. 执行风险分析
C. 估算项目成本
D. 定义活动
【单选题】
你要从另一名项目经理手中接管一个项目,你发现了关于该项目的如下信息:活动 Z 的最早开始日期为 15号,最晚开始日期为 20 号。活动 Z 很困难,其成本绩效指数(CPI)为 1.1,进度计划执行指数(SPI)为 0.8。该项目共有 11 名相关方。根据如上信息,你最关注的问题是:
A. 进度
B. 浮动时间
C. 成本
D. 可用资源数量
【单选题】
意料之外的技术问题需要添加三个新的项目资源。现有团队表现良好,但由于不能跟团队新资源分享关键信息,导致落后于进度。项目经理应该怎么做?
A. 指示所有团队成员查看沟通管理计划。
B. 与新资源开会,说明基本规则并要求妥协。
C. 要求职能经理指示新团队成员遵循相关方管理计划。
D. 开展团队建设活动,鼓励人际关系纽带
【单选题】
项目经理利用一种进度网络分析技术,为每项活动都定义了可能的活动工期分布范围,项目经理应该使用下列哪一项技术来计算整个项目的可能结果分布?
A. 资源平衡
B. 蒙特卡洛分析
C. 关键链技术
D. 因果分析
【单选题】
在项目执行过程中,一名相关方希望知道谁有权分配项目资源,为了解决这个问题,项目经理应该怎么做?
A. 与该相关方一起审查项目章程
B. 与该相关方一起检查沟通管理计划
C. 与该相关方一起审查资源管理计划
D. 获得相关方的一致同意,并更新相关方登记册
【单选题】
项目已经完成了第一个阶段的工作,现在刚进入第二个阶段。为了使第二个阶段的工作能够得到各相关方的支持,项目经理决定组织团队成员再次开展识别相关方过程。这个过程最有可能输出以下哪个成果?( )
A. 相关方登记册
B. 相关方参与度评估矩阵
C. 变更请求
D. 效益管理计划
【单选题】
施工工地受到风暴破坏. 因而,项目经理授权采购替代材料以及获得额外的资源,确保让项目保持进度,作此决定时,项目经理利用了下列哪一份文件?
A. 风险管理计划
B. 库存管理计划
C. 采购计划
D. 质量管理计划
【单选题】
在推出新产品期间,一个外部供应商导致大幅延期,延期可能导致项目终止。为解决这种情况,项目经理应该首先做什么?
A. 与多名外部供应商开会,产生问题的解决方案
B. 执行正确的工具和技术,在识别问题后尽快解决问题
C. 识别其他能够提供类似产品的外部供应商
D. 评估风险对项目的影响,实施风险应对计划,并与相关方沟通
【单选题】
一家施工公司为一个建筑项目部件采购召开投标人会议。受到投标人的建设书并评审。其中一个供应商提出非常优惠的价格,但是根据内部专家判断,该价格对于开展持续性的业务是不现实的。项目经理接下来应该怎么做?
A. 让供应商提供成本结构的补充信息
B. 让采购部门迅速签订合同
C. 在合同中增加处罚条款,确保供应商履行义务。
D. 相应地更改成本基准
【单选题】
项目进入了收尾阶段。项目发起人与客户组成的项目验收小组认为其中的一个可交付成果不符合验收标准。项目管理团队经过分析后,也认为的确是不符合验收标准。如果下列哪个过程做得更好,就可以避免这个问题?( )
A. 创建 WBS
B. 收集需求
C. 确认范围
D. 控制质量
【单选题】
哪些工具和技术可以用来监督风险?
A. 风险审计,检查和状态会议
B. 状态会议,风险登记册和风险重新评估
C. 状态会议,偏差和趋势分析和变更请求
D. 风险审计,储备分析和状态会议
【单选题】
项目经理获得供应商回复,并选择了一名供应商提供项目的其中一个关键组成部分。项目经理完成的是下列哪一个过程?
A. 管理采购
B. 指导和管理项目工作
C. 规划采购管理
D. 实施采购
【单选题】
某人已经被委派为项目经理,负责产品总装线的设计与建设项目。今天,他接到了一个重要相关方的询问。公司生产部门经理想了解用于配合该总装线的一个设施的建设是不是本项中的建设内容。为了给出准确的答复,项目经理应该查看在以下哪个过程中开发的文件?( )
A. 估算活动持续时间
B. 确认范围
C. 定义范围
D. 制订进度计划
【单选题】
在对公司至关重要的项目中,公司委派经验丰富且经过认证的项目经理替代没有经验的项目经理。采取这个措施的目的是为了确保不会因为项目经理缺乏经验而给项目的成功带来不利影响。这是采取哪一类风险战略?
A. 风险减轻
B. 风险接受
C. 风险回避
D. 风险转移
【单选题】
目前有两家公司要签署一个固定价格加奖金的合同。双方已经谈妥:合同的目标成本是 200,000 美元,目标费是 30,000 美元,因此合同的目标价格是 230,000 美元。买方还设定了 270,000 美元的最高价以及七三开的分成比率。如果卖方以 170,000 美元的实际成本完成了合同,除了合同的成本外,买方还要付给卖方多少费用?
A. 21,000 美元
B. 35,000 美元
C. 39,000 美元
D. 51,000 美元
【单选题】
下列哪一项与实施采购过程相关?
A. 获取卖方答复,选择卖方并授予合同的过程
B. 制定项目购买决议,确定方法和识别潜在卖方的过程
C. 完成每个项目采购的过程
D. 管理采购关系,监督合同履行以及做出所需变更和更正的过程